How long does it take to finish a basement?

Six weeks for a standard finish, eight to ten for a legal apartment — if the project is run on a schedule. Here's exactly where those weeks go, and the three things that quietly add a month when nobody's managing them.

The week-by-week timeline

WeekWhat happensInspections
Before week 13D design, fixed bid, permit application (city review runs 1–3 weeks — overlapped with planning, so it rarely adds calendar time)
Week 1Materials staged, framing goes up — the fastest visual progress of the project
Weeks 2–3Electrical, plumbing, and HVAC rough-ins by licensed trades; egress window cut if needed4-way rough inspection
Week 4Insulation, then drywall: hang, tape, mud, textureInsulation + drywall screw
Week 5Paint, doors, trim, cabinets — the “it looks like a house now” week
Week 6Flooring, fixtures, hardware, punch listFinal inspection

What actually causes delays

Apartments take 8–10 weeks

A legal basement apartment adds a kitchen, a separate entrance, fire separation, and a city registration — roughly two to four extra weeks, mostly in the kitchen and the entrance work.