| Week | What happens | Inspections |
|---|---|---|
| Before week 1 | 3D design, fixed bid, permit application (city review runs 1–3 weeks — overlapped with planning, so it rarely adds calendar time) | — |
| Week 1 | Materials staged, framing goes up — the fastest visual progress of the project | — |
| Weeks 2–3 | Electrical, plumbing, and HVAC rough-ins by licensed trades; egress window cut if needed | 4-way rough inspection |
| Week 4 | Insulation, then drywall: hang, tape, mud, texture | Insulation + drywall screw |
| Week 5 | Paint, doors, trim, cabinets — the “it looks like a house now” week | — |
| Week 6 | Flooring, fixtures, hardware, punch list | Final inspection |
A legal basement apartment adds a kitchen, a separate entrance, fire separation, and a city registration — roughly two to four extra weeks, mostly in the kitchen and the entrance work.